Bridge Crane for Tube Reactor Handling
Lifting Capacity 5~800 ton
Lifting Height 12-22 meter
Span 10.5~31.5 meter
Working Duty A5-A6
Ambient Temperature -20~40℃
Lifting Capacity 5~800 ton
Lifting Height 12-22 meter
Span 10.5~31.5 meter
Working Duty A5-A6
Ambient Temperature -20~40℃
Lifting Capacity: 75t~320t
Span: 10m~40m
Lifting Height: 15m-30m
Work Level: A7~A8
Type:QD
LiftingCapacity:5~800ton
LiftingHeight:12-22meter
Span:10.5~31.5meter
WorkingDuty:A5-A6
AmbientTemperature:-20~40℃
The main structure includes main beams, trolley traveling mechanism, electric trolley, hoisting mechanism, etc. Two double beams are the main supporting structure. With high quality steel, they have a strong frame that can withstand high pressure and bending when lifting heavy loads.
Tools: Wrench tool box, tow rope, gear oil, forklift, truck crane. Installation guide of Bridge Crane with Double Rail Trolley Hoist: Fill the gearbox oil – electric cabinet installation – end carriage connection – buffer installation – festoon track inst
Tools you need to prepare before installation: Wrench tool box, tow rope, gear oil, forklift, truck crane, etc.

The installation steps as below:
Fill the gearbox oil – electric cabinet installation – end carriage connection – buffer installation – festoon track installation – festoon installation – maintenance cage installation – Beam hoisting&Installation – Trolley hoisting&Installation – Crab Hoist Trolley installation – festoon cable connection – conductor rail installation – installation completed.
There is a installation guide video for your understand the installation more intuitively.